Hooray for the Solar Array


The Solar Panels are Installed...Only 75 more steps or so to go...

Wednesday & Thursday the crew from All Energy Solar installed the system.

Before

We've only been waiting since the end of March. The loan company had to run another credit check to approve a 60 day extension. 

Here are the things between us and generating our own solar electricity:

  • Electrical Inspection - 10/5
  • Building Inspection - to be scheduled
  • Submit documentation to Xcel
  • Xcel finalizes documentation and orders a bi-directional meter 
  • Once the meter is ordered, I'll schedule your meter installation with Xcel - the appointment when we turn your system on!
  • We'll configure your monitoring and send you the links so you can see your energy production on any internet browser.
  • I'll schedule your closeout visit with Colin to walk through your monitoring, and warranty, and answer any final questions. 

It is absolutely maddening.

Meanwhile, all the sunflowers except these are now pretty much exhausted:



The tomato beds are finally producing quite a few large tomatoes. There's a steady zucchini pump (2-3 per week), and we're getting a few red bell peppers along with some banana peppers. 

The weather has not yet turned to fall. Today should get to 79 degrees, but then next week is low 70's as far as the eye can see. Not terrible for October, though the days grow shorter.

A thing I would like to replicate next year is the very successful flower planting I did after the snap peas were exhausted. 


This weekend: Heavy bulb planting.

That is all. 









 


Comments

Popular posts from this blog

Stairway Complete; Fruit & Vegetable Season Begins

In which I magically make 5 pounds of tomatoes disappear

Trains, Canoes, and Automobiles